Super Structures LearningA Super Structures company
← Preventing Overruns

Building and Keeping a Skilled Crew

Building and Keeping a Skilled Crew

Welcome

Hello, and welcome. This is Super Structures General Contractors — a national general contractor headquartered in Powhatan, Virginia — here to help you and your clients build something that lasts. We're glad you're with us, and we look forward to connecting with you.

Alright, Building and Keeping a Skilled Crew. Don't let the plain title fool you. Here's the part that actually matters on the job: A labor shortage breaks the production rate your estimate assumed, so training and retention are budget lines, not favors. Learn it well and you'll spend less keeping good people than you are spending today replacing them.

A mechanical contractor lost two of its five journeymen in a spring hiring wave to a competitor paying $3 more an hour. The remaining crew ran overtime for eleven weeks to hold the schedule on two jobs. Overtime premium, lower production from tired people, and callbacks on work done by the apprentices who were suddenly working alone cost roughly $71,000. Matching the raise for all five journeymen would have cost about $31,000 a year. The owner said afterward that he had known the market rate had moved. He just had not done the math, and nobody in the company owned the number.

How a shortage becomes an overrun

The estimate assumed a production rate: so many units per crew-hour, by a crew of a certain makeup. Fewer qualified people means:

Develop the workforce you need

Retention is cheaper than replacement

Replacing an experienced tradesperson costs weeks of recruiting, lost production while the new hire learns your methods, the rework a new person makes, and the time your best lead spends training instead of producing. Many contractors put the total at a third to a half of a year's wages. The retention levers that work in the trades:

Going Deeper (Intermediate)

Measure it. Track overtime as a percent of hours, turnover by crew and by superintendent, and rework hours by cost code. When overtime runs above 10 percent for more than a few weeks, you are not short on hours, you are short on people, and the fix is hiring or rescheduling, not more Saturdays. Exit conversations, done honestly by someone other than the person's supervisor, tell you which superintendent people leave and which one they follow.

Put a number on ramp-up. A new journeyman is typically at 60 to 70 percent of a veteran's production for the first month on your crews, even if they are skilled, because every company's methods and layout differ. Budget for it on the job where the new hire lands, or the job will show an overrun that is really a hiring cost.

Advanced / Pro-Level

Pros treat the labor plan as part of the bid. Before committing to a start date they check the company-wide crew calendar, not just this job's schedule, because the overrun on this job is often caused by the job before it. They keep a short list of pre-qualified subs or labor partners for the trades they self-perform, so a shortage becomes a cost decision made in advance instead of a schedule failure discovered in the field. They pay the market rate before the competitor does, because a raise given is cheaper than a raise matched after the resignation, and the ones who leave are never the ones you could spare.

They also build culture on purpose: a safety program people believe in, foremen trained to lead and not just to build, recognition that is specific and public, and an honest answer when someone asks what their path is. None of that shows up on a cost report, and all of it shows up in turnover.

Practice Challenge

Your three best field people are a superintendent, a lead carpenter, and a concrete foreman. For each, estimate the cost to replace them (recruiting, ramp-up, lost production, your time) and name the one change most likely to keep them. Add it up. (Answer: there is no single right number, but most companies land between a third and a half of annual wages per person, often $25,000 to $50,000 each, so $75,000 to $150,000 for the three; that total is your retention budget, and the one change is usually pay reviewed against market, a predictable schedule, a path to the next role, or a different superintendent; whatever it is, it costs less than the total.)

In Practice

One contractor reviews pay against market every spring, trains an apprentice on every crew, and keeps its people. Another finds out the market moved when the resignations arrive, then pays overtime for eleven weeks and loses the referral job because the apprentices' work had to be redone.

Common Mistakes to Avoid

Takeaway: A labor shortage breaks the production rate your estimate assumed, so training and retention are budget lines, not favors.

Educational content — not legal, financial, or contractual advice. Every project and contract is different; follow your contract documents, your company's procedures, and the advice of your attorney, CPA, and surety.

Sign in to track your progress