Structural Sheets: The S Series
Welcome
Hello, and welcome. This is Super Structures General Contractors — a national general contractor headquartered in Powhatan, Virginia — here to help you and your clients build something that lasts. We're glad you're with us, and we look forward to connecting with you.
Alright, Structural Sheets: The S Series. Don't let the plain title fool you. Here's the part that actually matters on the job: The S sheets tell you what holds the building up and exactly where it bears, and nothing on them can be built until the structural dimensions and the architectural dimensions agree. Learn it well and you'll catch the footing in the wrong place while it's still a string line instead of a jackhammer.
Structural sheets are drawn by the engineer of record over the architect's gridlines, and they are the sheets the special inspector holds against your work. Here is how a superintendent reads them on our four-story apartment set.
General notes, design loads, and the abbreviations
S-001 and S-002 are text sheets, and they govern everything that follows. Read them before the foundation plan.
- Codes and loads — the IBC edition as adopted locally, floor live loads (units at one value, corridors and balconies higher), roof and snow, wind, seismic design category.
- Soils — the allowable bearing pressure and the geotechnical report by number and date.
- Concrete — strength by element, reinforcing per ASTM A615 Grade 60, lap splice and hook tables, cover.
- Steel, masonry, and wood — ASTM grades, masonry strength, lumber species and grades, truss design criteria (trusses are a deferred submittal), fastener and hold-down requirements.
- Abbreviations — EW (each way), EF (each face), T&B (top and bottom), CONT, T/F (top of footing), T/S (top of slab), SW (shear wall), HD (hold-down).
Foundation plan and the footing schedule
S-101 shows the gridlines, continuous wall footings as dashed lines below the wall, and spread footings as dashed squares with a footing mark (F3.0, F4.5). The footing schedule decodes each mark: plan size, thickness, reinforcing (4'-0" x 4'-0" x 12", (5) #5 each way), and often the top-of-footing elevation. Step footings are drawn where grade changes, with a typical step detail. On a wood-frame apartment building the plan also carries hold-down tags keyed to a schedule of anchor sizes and embedment, and anchor bolt spacing in a general note.
What to check: top-of-footing elevations against the grading plan and your locality's frost depth; whether footings are centered on grid or offset; dowels from footing to wall; and every embedded anchor before the pour.
Slab-on-grade and reinforcing
The slab notes give thickness (4 inches typical in units, thicker in the garage), reinforcing (welded wire or bars each way, or fiber), the vapor retarder, the compacted base, and the control joint layout: maximum spacing both ways and saw-cut depth. Thickened slabs under bearing walls are drawn as dashed bands with a section — say 12 inches deep by 24 wide with two continuous #5 bars. Depressions at showers and the entry mat are hatched with a depth note.
What to check: thickened slab locations match the bearing walls on the framing plan above; the joint layout is drawn or is yours to submit; the wire or bars have chairs specified so they end up where the engineer drew them.
Framing plans by level
S-201 through S-204 are the framing plans. First read the convention note: on most sets, the Level 2 framing plan shows the framing that supports Level 2 — the walls below and the trusses under that floor. On this wood-frame set each plan shows bearing walls by hatch, floor truss span direction and depth with the truss manufacturer named as designer, beam marks (B1, B2) keyed to a beam schedule, posts, and shear wall tags (SW1, SW2) keyed to a schedule, with straps and hold-downs at openings and wall ends.
What to check: bearing walls and shear walls stack from level to level, and every post has a load path to a footing. A bearing wall that moves 6 inches between floors shows up as a sagging corridor.
Column, beam, and header schedules with sections
The schedules convert marks into members. The header schedule gives a header size per opening width. The beam schedule gives each mark's size, species or steel shape, and connections. The shear wall schedule gives sheathing thickness, nail size and spacing at edges and field, sill anchorage, and the hold-down at each end — the schedule the inspector checks with a nail gauge. On a podium or steel-framed building the column schedule reads as a table with gridlines across and levels down: size, splices, base plates, anchor rods. Sections (S-301) cut the foundation wall, the podium slab, or the stair and show rebar each face, wall thickness, and bearing. Typical details (S-501) cover corner bars, wall intersections, step footings, slab joints, and hold-downs.
Special inspections and agreeing with architectural
IBC Chapter 17 requires a statement of special inspections: soils at bearing, reinforcing placement before each pour, concrete sampling and strength, post-installed anchors, welding and high-strength bolting, wood shear walls and diaphragms where required, sprayed fireproofing. The super schedules these, and a pour without the required inspection is a pour the engineer may reject.
Agreement with architectural is a daily check. Structural dimensions to gridlines and to face of concrete or stud; architectural may dimension to face of finish. Compare the overall and grid-to-grid dimensions on S-101 and A-101, the level datums on A-301 against the top of sheathing on the framing plans, and opening widths against the header schedule. A difference is an RFI, not a judgment call.
Going Deeper (Intermediate)
Learn to read a rebar callout cold. #5 @ 12" EW T&B is number 5 bars at 12 inches each way, top and bottom. (2) #5 CONT is two continuous bars. LAP 40 BAR DIA sets the splice length from the table in the notes. Clear cover is typically 3 inches against earth and 1 1/2 inches in formed surfaces, per ACI 318 and the notes. Rebar placing drawings are a shop drawing made from the S sheets; when they disagree, the S sheets govern until the engineer says otherwise.
Advanced / Pro-Level
Pros build an embed list for every pour from all disciplines: hold-down anchors and bolts from S, depressions from A, sleeves and stub-ups from P and E, conduit for the fire alarm and telecom pathways, checked against the formwork before the special inspector arrives. They plan the pour sequence around construction joints the engineer has shown or approved, and keep the geotech on call so the footing inspection and the soils inspection happen in one visit.
Practice Challenge
Footing F3 at grid C-4 is scheduled at 3'-6" square, 12 inches thick, top of footing 97'-0". FFE 100'-0" equals civil 412.50, and finished grade at that corner is 411.90. Say your locality requires 18 inches of frost cover. Does the footing comply, and what is its bottom elevation in civil terms? (Answer: top of footing 97'-0" is 3 feet below the floor, so 412.50 minus 3.00 is 409.50; the bottom is 12 inches lower at 408.50. Finished grade 411.90 minus 408.50 puts the bottom 3.40 feet, about 41 inches, below grade, well past 18 inches. It complies, and you checked it by converting to decimal feet, not by eye.)
In Practice
A super who overlays S-101 on A-101 on day one finds the 2-inch disagreement at the stair before the surveyor stakes it. A super who trusts the surveyor to sort it out finds it when the stair stringer will not fit.
Common Mistakes to Avoid
- Reading the foundation plan before the general notes that govern it
- Pouring without the special inspection the table requires
- Letting the bearing wall drift between the framing plan and the floor plan
- Missing an embedded anchor until after the pour
- Assuming the framing plan shows the level you are standing on
Takeaway: The S sheets tell you what holds the building up and exactly where it bears, and nothing on them can be built until the structural dimensions and the architectural dimensions agree.
Educational content — not legal, safety, or contractual advice. Follow your company's procedures, your contract, and the OSHA and local requirements that apply to your site.